The land acquisition process has been implemented in accordance with the planning set for 2016. The table below shows the overall information on the progress of land acquisition being implemented.

Infrastructure Construction
By the end of December 2016, four (4) contracts of tertiary irrigation infrastructure were offered to successful contractors. Of the four (4) contracts offered, four (4) blocks of irrigation have been completed. Details of the progress of the construction work carried out are as follows:

Repair and Restoration of Irrigation and Drainage Infrastructure
A total of RM15,000,000 has been allocated to carry out repair and rehabilitation works on irrigation and drainage infrastructure by 2016. The breakdown of expenditure by components of the work done in 2016 is as follows: