MADA INFRASTRUCTURE CONSTRUCTION DEVELOPMENT PROGRAM

A.DEVELOPMENT AND MAINTENANCE OF INFRASTRUCTURE OF IRRIGATION AND DRAINAGE
Most irrigation and drainage infrastructure of MADA was built 30 to 50 years ago. These structures have disappeared due to intensive use and natural erosion factors. There are some of these older structures that need to be replaced with new ones. The lack of maintenance provision has limited the quality and maintenance level of maintenance. Additionally, the function and use of these structures need to be improved and modified to meet current requirements. Repair work should be carried out as soon as possible to avoid further damage and catastrophic events. In 2016, MADA has acquired two (2) sources of allocation to carry out development projects namely:

i. The First Rolling Plan (RP1) allocation under the 11th Malaysia Plan (11MP)
In 2016, a total of RM7.1 million has been approved to undertake development projects under the RM1 11th RP1. The list of projects and the breakdown of the provisions are as follows:

Development Allocation Received In First Rolling Plan (RMK11)

In 2016, under the Rebuilding & Upgrading of Irrigation And Drainage Structures, the MADA has built and completed a control structure to replace Tandop Tailed Alor Melaka, Region II, MADA. These ceilings are expected to be completed and will be operational by mid-2017.

For the Water Treatment Flood Upgrade Project, the MADA has carried out three (3) scopes of work namely increasing the drainage capacity, building a small water control structure and strengthening the slope downstream of the main structure. Among the work done is to deepen and elevate the Sg. Gial / Sg. Kangar is expected to be completed by 2017, constructing and completing the structure to stabilize the downstream slope of the Kuala Sanglang Lama Tilted Tiling with completed steel sheeting in November 2016 and then work on building and upgrading small control structures in each region.

REBUILDING & RECOGNIZING THE IRRIGATION AND DRAINAGE STRUCTURE

Building And Setting Up A Control Structure To Replace Tide Blocks Alor Melaka, Region II, MADA



IMPROVING WATER WAYS FOR AGRICULTURE FLOODS AGRICULTURAL AREA

Work to Deepen and Elevate the Gial River / Kangaroo River And Related Workers In Region I, MADA


Building And Completing Structure To Stabilize Slope Downstream of Hilir Tandop Pasang Surut Kuala Sanglang Lama Wilayah I Dan II, MADA



ii. NKEA Project EPP 10: Scaling and Enhancing Productivity On Paddy Plants In Muda Areas
In 2016, the Project Development and Management Division has received a financial allocation of RM 89,000,000 to undertake the development of tertiary irrigation systems and the restoration / improvement works of irrigation and irrigation infrastructure under the NKEA Project EPP 10. The allocation provisions of components are as in the following table:


Land Acquisition
The land acquisition process has been implemented in accordance with the planning set for 2016. The table below shows the overall information on the progress of land acquisition being implemented.

Infrastructure Construction
By the end of December 2016, four (4) contracts of tertiary irrigation infrastructure were offered to successful contractors. Of the four (4) contracts offered, four (4) blocks of irrigation have been completed. Details of the progress of the construction work carried out are as follows:

Repair and Restoration of Irrigation and Drainage Infrastructure
A total of RM15,000,000 has been allocated to carry out repair and rehabilitation works on irrigation and drainage infrastructure by 2016. The breakdown of expenditure by components of the work done in 2016 is as follows: